Politics & institutions
America Has a Permitting Problem
It’s Time for a Diagnosis
Read Here
From Heavy Lifting · Public feed content · Heavy Lifting
This piece is co-authored with Tim Doyle, President and co-founder (with me) of the Responsible Business Initiative.
A natural-gas pipeline can hold a federal certificate and still lose essential companion authorizations in court. An offshore wind farm can secure federal approvals, invest billions in construction, and then be ordered to stop work by a later administration. The projects serve different energy markets and attract different political supporters. Yet they expose a common weakness: obtaining an approval and being able to rely on it are not necessarily the same thing. There are legitimate reasons for courts to overturn defective decisions and for agencies to respond to new evidence. There is no good reason to confuse the mere issuance of a permit with the ability to finish a project.
That distinction matters because America has to build things. A great many things, in fact, and for reasons that do not fit neatly into our usual political categories.
Households want affordable electricity. Utilities have to deliver reliable power during heat waves, severe storms, and rising demand. Businesses are racing to establish the data centers, factories, and supply chains needed for artificial intelligence (AI) and advanced manufacturing. At the same time, many states, companies, and investors have committed to cutting emissions, and communities are already rebuilding after floods, fires, and storms. That means power plants and electricity networks, but also water systems, wildfire defenses, flood protection, mines, pipelines, ports, and other facilities whose consequences reach well beyond the sites where they are built. None comes into existence because a government announces a goal or a company announces an investment. Announcements are abundant; functioning infrastructure is a different asset class.
The United States is extraordinarily good at inventing technologies and mobilizing capital. Bringing those inventions into physical operation is another matter. A breakthrough in geothermal drilling produces no electricity until someone obtains rights to the land, drills, connects the plant to the grid, and operates it. A proposed transmission line cannot move a single electron. The economic promise of AI depends not only on chips and software but also on electricity, cooling, network connections, and the facilities that house them. When a hyperscale data center arrives in a community, it can promise jobs and tax revenues while also prompting entirely reasonable questions about water use, substations, and who will pay for the electrical upgrades. As one of us (Bob) has written about the bipartisan opposition to AI data centers, political labels explain surprisingly little when a large industrial load arrives down the road. The other of us (Tim) reads the same pattern differently. Opposition from both parties is not a consensus, and much of it, like much of the support, turns more on politics than on the economics of a particular project. Before a community opposes every data center or welcomes all of them, residents, officials, and developers need a shared account of what a given project would bring and what it would cost.
There is also the competition with China. The country is expanding renewable power, fossil-fuel infrastructure, manufacturing capacity, and the industrial systems that support them. As one of us argued with Nick Loris in China Is No Green Energy Darling, China’s energy strategy cannot be understood as a choice between green energy and fossil fuels. China seeks energy security and industrial advantage. According to the International Energy Agency, it added nearly 370 GW of solar and 117 GW of wind in 2025 while commissioning almost 80 GW of coal capacity. Those technologies do different jobs, but together they demonstrate the scale of construction. The country often uses governmental powers that Americans would rightly resist. We should not envy the absence of democratic accountability. But neither should we excuse avoidable delay as the price of accountability, because most of it comes from how our laws and agencies work, not from the Constitution’s checks.
The conventional account of America’s permitting problem is straightforward. Environmental review under the National Environmental Policy Act (NEPA) takes too long, and the answer is to streamline it. NEPA certainly matters. It has also been revised by successive administrations, amended by Congress, and interpreted by the Supreme Court, while complaints about slow infrastructure development continue. The evidence suggests a less convenient diagnosis. Projects depend on chains of decisions that no single institution reliably coordinates; those institutions sometimes lack the people and information needed to do their jobs; the choices involve real interests that cannot all prevail; and even completed approvals can prove precarious. Different causes require different treatments.
One statute cannot cure all four. The proposition now has a live test. On September 30 the Republican Chairs and Democratic ranking members of the Senates’s Senate’s Energy and Natural Resources and Environment and Public Works committees introduced the Bipartisan American Affordability and Jobs Act, which reaches well beyond NEPA. On November 9, the Senate voted 73 to 25 to take it up; ten days later it passed the bill 62 to 33, with a manager’s amendment that, among other things, cut the FAST-41 limitations period to 150 days and softened provisions on tribal historic preservation. The bill now goes to a House where members of both parties want changes, and any change would send it back to a Senate whose coalition had already shrunk by eleven votes, with the 119th Congress ending on January 3.
This essay builds on our July 2026 Responsible Business Initiative study, The Cost of Delay: Federal Permitting and America’s Energy Challenge. We are not offering a legislative prescription here. We want to establish what the problem actually is. The place to begin is with the extraordinary distance between the infrastructure America plans and the infrastructure it manages to bring into service.
The Gap Between Plans and Projects
The United States does not suffer from a shortage of infrastructure proposals. Its difficulty is turning proposals into projects that are built and running, which requires land, equipment, capital, skilled labor, utility connections, public authority, and sometimes the consent—or the resolution of objections—of people who bear costs that others do not. Figures about energy capacity and construction cannot establish how much of the gap is attributable to permitting, but they reveal how much is at stake in getting the whole process to work.
Start with transmission. According to a revised report by Americans for a Clean Energy Grid and Grid Strategies, the United States built an average of 1,781 miles a year of new transmission lines rated at 345 kilovolts (kV) or above during 2010–2014. That fell to 942 miles during 2015–2019 and 536 miles during 2020–2024. The corrected figure for 2024 alone is 888 miles, but one better year does not erase the decline. The electric system is being asked to accommodate new generating locations, new industrial loads, and new patterns of demand while construction of its most important long-distance arteries has slowed sharply.

The U.S. Department of Energy (DOE)’s 2023 National Transmission Needs Study reports that the studies it reviewed would need within-region transmission to grow by a median of 20% by 2035 if demand and clean energy grow moderately, 64% if clean energy grows quickly, and 128% if both grow quickly. These figures measure capacity over distance, not miles of line; both measures belong in the discussion, but not on the same chart. A more immediate consequence of inadequate networks is congestion. Electricity that could be generated economically cannot always reach the customers who need it. Grid Strategies estimated more than $17 billion in U.S. transmission congestion costs in 2025, an industry estimate equivalent in magnitude to roughly 3% of national retail electricity revenues. The comparison is not a claim that permitting added 3% to household bills, but it does show that the network’s limitations have material economic consequences.
Generation and storage display considerable ambition. The U.S. Energy Information Administration (EIA) reports that developers added 53 gigawatts (GW) of utility-scale generating and battery capacity in 2025, and planned 86 GW for 2026, a record if realized. The 2026 plan was led by solar at 43.4 GW, battery storage at approximately 24 GW, and wind at 11.8 GW. These are gross capacity additions, not interchangeable amounts of dependable electricity, because a gigawatt of solar, a gigawatt of battery discharge, and a gigawatt of gas generation serve different functions. But all require physical locations, equipment, networks, and decisions that allow construction to proceed.
The scale of what developers hope to construct is even larger. Lawrence Berkeley National Laboratory’s interconnection-queue survey counted about 8,200 projects at the end of 2025, representing 1,312 GW of proposed generation and 749 GW of storage. That combined 2,061-GW figure is striking, but the queue is a contest for access to the grid, not a list of projects already financed and awaiting a federal permit. Many entries will be withdrawn. The important point is that a system receiving so many proposals needs credible ways to distinguish projects that can proceed from those that cannot, and to connect the successful ones on a workable timetable. The Federal Energy Regulatory Commission (FERC) has responded with reforms to interconnection studies and long-term regional transmission planning. Those are serious infrastructure questions largely outside NEPA’s statutory purpose.
Data centers intensify the challenge. Berkeley Lab estimated that all U.S. data centers consumed 176 terawatt-hours (TWh) of electricity in 2023, or about 4.4% of national electricity use. Its more recent assessment projects a 9.5%–15.3% share by 2030, with an 11.8% central estimate. These figures cover all data centers, not AI alone, and they are scenarios rather than certainties. Even the lower end would represent a substantial change in the geography and scale of electricity demand. The facility itself may be permitted locally while the generation, transmission, and substations needed to serve it depend on entirely different decision-makers.

Sources, definitions, and measurement notes for Table 1 are in Appendix B.
The financial scale is equally substantial. The Edison Electric Institute (EEI) says its investor-owned utility members will invest nearly $1.4 trillion over the next five years on generation, networks, and related infrastructure. That is an industry capital-spending outlook, not an estimate of money lost to permitting delays. Climate adaptation adds another range of investments, from flood defenses and wildfire protection to water systems and grid hardening; their benefits and physical measures vary too much to collapse into an honest national gigawatt target.
The country has ideas, plans, and substantial capital. Whether it turns those into functioning infrastructure depends on a system that is much larger than the familiar environmental-review debate. Before examining that system, we should look at the statute that dominates the argument about reform.
NEPA: The Usual Suspect
Signed into law by Richard Nixon on January 1, 1970, the National Environmental Policy Act requires federal agencies to evaluate environmental effects and alternatives when they take certain major actions. Projects likely to have significant effects generally require an environmental impact statement (EIS). NEPA is a procedural law: it governs analysis and disclosure, not whether a project must ultimately be approved. Nor does completing a NEPA review, by itself, confer permission to build. Nevertheless, for a controversial project the environmental record may be central to agency authorizations, design changes, consultation, and litigation. Those who complain that the process can consume years are not inventing the problem.
But a detailed review is sometimes exactly what makes the eventual decision better. The Gemini Solar project in Nevada, for example, emerged from federal environmental review with a design modified in response to wildlife and other concerns, and ultimately entered service in 2024. The lesson is not that review is always efficient; it is that review can change what gets built for defensible reasons. SunZia, the major southwestern transmission project, presents a different problem. (Appendix A provides more details on these projects and four others.) A dispute involving the Defense Department and White Sands Missile Range required further assessment and design changes, while other approvals and sponsor decisions shaped the project’s long development. It would be inaccurate to treat the entire elapsed history as one prolonged NEPA review. The project’s obstacles were interlocking, not interchangeable.
Indeed, few parts of federal infrastructure decision-making have been revised so repeatedly. Regulations changed under Trump’s first administration and again under Biden. Congress amended the statute in the bipartisan Fiscal Responsibility Act of 2023, addressing deadlines, page limits, and lead-agency coordination. The Supreme Court’s 2025 Seven County decision emphasized judicial deference to agencies’ judgments about the scope of environmental analysis. The second Trump administration rescinded government-wide Council on Environmental Quality regulations, with its final action effective in January 2026. The President revoked the 1977 order behind those regulations in order, as his order put it, “to expedite and simplify the permitting process.” Those changes are significant, and it is too early to assess their full consequences. Congress may now go further. As introduced, the Senate bill would set deadlines of two years for an environmental impact statement and one year for an environmental assessment, with consequences for agencies that miss them. But the continuing debate suggests that NEPA has received far more attention than the many constraints it was never designed to address.
Even measurement of the review process deserves more attention. Government studies have reported different median completion times using different populations and different endpoints; an older measure ran to the record of decision, a newer one to the final environmental impact statement. They cannot be assembled into a clean trend without adjusting for those differences. The underlying studies and dates are documented in our earlier research. What matters for this argument is that a completed review is only one event in a project’s life, and elapsed time by itself does not tell us whether that event delayed the eventual opening.
A badly prepared environmental assessment can generate lawsuits and years of rework; a careful one can identify a better route or avert damage that the public would otherwise bear. Reform should distinguish productive review from needless delay. It should also recognize how often the binding obstacle is somewhere else. That requires looking behind the signature.
The Invisible System Behind the Signature
Imagine a transmission developer trying to connect two regions across several states. The company needs a route, land rights, financing, equipment, and agreement on who benefits and who pays. State commissions may decide siting questions separately, sometimes with different legal standards. Federal land crossings can require federal authorizations and environmental review. Tribal governments may hold legally protected interests and consultation rights. Counties and municipalities may regulate associated facilities. A regional grid operator must determine technical connections and costs. A court can review a decision after it is made. No single officer can simply stamp this bundle of questions “approved.”
What we call permitting actually includes distinct activities. Environmental review examines effects and alternatives. Substantive permits and authorizations decide whether particular activities may lawfully happen. State and local siting decisions address land use, utilities, water, and other responsibilities. Tribal consultation involves rights, obligations, and the quality of government-to-government engagement. Interconnection, procurement, and financing can make or break a project even after public approvals have been obtained. Each has different decision-makers and possible remedies. No one-size reform makes them the same.
The federal allocation of authority illustrates the point. The Department of the Interior (DOI) oversees extensive public-land and offshore-energy decisions through agencies including the Bureau of Land Management (BLM) and the Bureau of Ocean Energy Management (BOEM). The Environmental Protection Agency (EPA) administers specialized environmental programs, including certain permits for underground carbon dioxide storage. DOE conducts analysis and exercises particular energy-related authorities, but it does not issue a universal permit for power plants. Federal Energy Regulatory Commission (FERC) certificates interstate natural-gas pipelines and regulates important parts of interstate electricity transmission and wholesale markets. The Army Corps of Engineers, wildlife agencies, states, tribes, and localities exercise other authorities. Appendix C explains the fuller map.
There are striking differences even between familiar infrastructure types. Interstate natural-gas pipelines generally go through a federal certification regime administered by FERC. Long-distance electricity transmission often depends more heavily on state siting decisions, negotiated rights-of-way, and allocation of costs across jurisdictions. An approach that clears a bottleneck for pipelines may have little effect on a transmission line that cannot obtain a state route or agreement about who should pay. Where States decide the route but federal rules decide who pays, the States need a defined role in the cost decision too.
Nor are the challenges confined to remotely located pipelines and power plants. A hyperscale data center may need no federal environmental impact statement at all. It can still be stalled by local zoning, access to water, utility service agreements, the timing of a substation, or the allocation of upgrade costs. Blaming every delay on the federal review system is rather like blaming every traffic jam on interstate highways, including the ones caused by a closed side street.
The most useful way to understand the interactions is the project’s critical path: the sequence of tasks that determines the earliest possible completion date. Suppose a federal authorization arrives in eighteen months but the last indispensable transformer cannot be delivered for thirty. Accelerating the federal decision by six months may look excellent on an agency dashboard and change nothing about when customers receive power. No permitting reform can shorten that wait, because it turns on how many transformers manufacturers can build, not on how fast agencies decide. Conversely, if the federal decision is the last outstanding requirement, six months could be decisive. The point is not to minimize legal approvals. It is to identify which decision, piece of equipment, or unresolved agreement actually controls completion—and who is responsible for coordinating the whole.
That is not chiefly a question of statutory word counts. It is a question about institutions, information, and the people asked to do difficult work.
The People Behind the Permits
Permitting discussions are full of statutes, deadlines, and organizational charts. Actual decisions require geologists, engineers, biologists, lawyers, data specialists, people capable of meaningful consultation with tribal governments, and experienced managers who can work across agencies whose responsibilities do not line up neatly. A complicated permit is not completed just because an agency has been given a shorter deadline. A statutory deadline does not hire a geologist. A deadline on one agency’s review also depends on approvals from other agencies, which need staff of their own.
EPA’s carbon-storage well program offers a concrete example. Permits under its Class VI program govern wells used for geologic storage of carbon dioxide and demand serious technical evaluation. According to the EPA inspector general, staffing assigned to the program rose from 15.25 to 37.7 full-time-equivalent positions between fiscal years 2021 and 2024, an increase of 147%. Pending applications rose by more than 2,800% over the same period. Even impressive hiring gains can be overwhelmed by a much faster increase in workload. The inspector general also reported that total underground-injection staffing grew only 5.6% over the period, so an organization can make one priority more visible without adding equivalent capacity across the institution.

Geothermal development reveals a similar problem from another direction. The Government Accountability Office (GAO) reported in October 2026 that acreage nominated for geothermal development on federal land grew from about 26,000 acres in 2020 to more than one million in 2025. The BLM faced vacancies, departures, competing demands on specialists, and weaknesses in its ability to track applications consistently across field offices. An agency that does not know where its applications stand is unlikely to manage their progress well, whatever deadline Congress assigns it. Applicants and agencies also need to agree at the outset on what a complete application contains, or the clock runs on paperwork rather than review. Technical knowledge also accumulates with experience. A senior official who knows whom to call in another agency can resolve a problem that an organizational chart makes look insoluble.
Government staff are not the only people who need capacity. States and localities administer crucial approvals, often alongside other pressing responsibilities. Tribes and affected communities must have the resources to understand proposals, review environmental records, and exercise their legal rights. In an offshore-wind oversight review, nearly all the tribal representatives GAO interviewed said they lacked adequate capacity to engage fully in consultation. A right to participate can become hollow when the people expected to exercise it lack the resources to do so. Speeding up a decision by making participation meaningless would solve the wrong problem.
There is a further institutional weakness that recurs in our research. The government publishes some review-time measures but not others; BLM has struggled to track geothermal applications across offices; there is no credible national count of unfilled permitting specialist positions or comparable nationwide assessment of administrative delay across all infrastructure types. Nor do existing studies give us a defensible number for the cost of capital caused specifically by permitting. These are not all the same data problem, and there are good measures in particular programs. Together they raise a question that deserves more attention: How does a country manage a complex approval system when it lacks a consistent account of where the system is failing? Reform ought to improve the instruments as well as the machinery.
Of course, adding staff and databases cannot settle disputes over which projects should proceed. That brings us to the most politically difficult part of the diagnosis.
The Politics of Trade-offs
Americans agree rather readily that the country should build infrastructure, and rather less readily about which infrastructure, where it should go, who should pay, what damage is acceptable, and who gets the final say. These are not details to be swept away by shortening an environmental impact statement. They are choices about benefits and burdens, some of which fall on people who receive little of the resulting benefit.
Consider transmission. A new line can carry low-cost electricity to distant customers, improve reliability, and connect generation that would otherwise be stranded. It can also cut through farms, forests, neighborhoods, and places of religious or historical importance. The benefits may be spread across several states while the visible impacts fall on a narrow corridor. Siting that limits what neighbors must see, and a share of the benefits for the communities that bear the burdens, belong in that conversation. It is not enough to invoke the national interest and dismiss those impacts. Nor can a local objection always determine an issue affecting millions of customers. Government has to resolve such conflicts through processes that earn legitimacy, not pretend that every constituency can get its first choice.
A lithium mine creates a different set of conflicts. Nevada’s Thacker Pass project largely survived challenges to its federal approvals but encountered a distinct state water-rights dispute, including a cease-and-desist order involving pumping, while construction continued. Tribal concerns persisted beyond the federal lawsuits. Those disputes involve different legal rights and decision-makers. A permit settles a legal question; it does not automatically settle a community conflict. The lesson is not that every objection should block a mine or that a mine needed for batteries should receive special immunity. It is that permitting has to confront genuine trade-offs whose consequences remain after the paperwork is signed.
Our political categories do not explain these choices very well. In its February 2026 construction outlook, EIA expected Texas to account for 40% of planned new U.S. utility-scale solar capacity and more than half of planned battery-power additions. Texas is not generally held up as a model of progressive climate politics. As one of us discussed in The Texas Power Paradox, the state’s actual electricity investment patterns do not sit comfortably inside the familiar partisan categories. The same complexity appears in Congress. A 2022 permitting package associated with Senator Joe Manchin failed to secure cloture, with opposition from senators of both parties; the Senate’s roll-call record is less tidy than a red-versus-blue story. The new bill tells a similar story, because its four lead sponsors are two Republicans and two Democrats, and the Senate’s first vote on it drew support and opposition from both parties. In 2023, Congress took an exceptional step to secure the Mountain Valley Pipeline’s outstanding authorizations. That choice will matter when we consider what makes decisions durable.
There is meaningful intellectual work across this divide. On the Ecoright, Nick Loris at C3 Solutions has argued that focusing on NEPA alone misses substantive permits, while ClearPath has emphasized the need to build energy infrastructure. The Center for Climate and Energy Solutions has worked with companies and other stakeholders to identify shared priorities for reform. These efforts do not imply agreement about particular legislation. They show that the problem cannot be assigned to one ideological camp, even if proposed solutions still divide it.
Environmental organizations face an especially demanding set of choices. Their record in protecting habitats, controlling pollution, and ensuring legal compliance is substantial, and lawsuits sometimes expose genuine failures by agencies. But an organization committed to reducing emissions also has to confront the consequences of opposing transmission, mines, or generation facilities needed for that objective. Protecting habitat beside a proposed line is a serious interest. So is connecting cleaner and less expensive electricity to consumers. Calling either concern illegitimate does not resolve the conflict.
The scale of environmental litigation is often invoked carelessly. A peer-reviewed analysis of more than 25,000 federal environmental civil cases from 1988 through 2022 found environmental advocacy organizations as plaintiffs in approximately 26%. That was a study across environmental laws, not a calculation of years of infrastructure delay attributable to nonprofit groups. The finding establishes their significant role in legal accountability, not that their cases are frivolous. The challenge is for developers, regulators, and environmental organizations alike to ask whether their choices resolve substantive problems or merely transfer them to another arena. Fewer suits are likely to arise when the law states more clearly what agencies must do.
Larry Selzer of The Conservation Fund put this in constructive terms in his Heavy Lifting essay “Three Eras”. He argues that after building conservation institutions and a powerful framework for pollution protection, the environmental movement faces a further task: making protection and responsible development compatible more often. That is a more productive challenge than declaring environmentalists the obstacle. It also asks them to grapple with a cost that is easy to ignore: who pays when a project proceeds, and who pays when it never does?
Sometimes better analysis, consultation, or design can reconcile interests. Sometimes there will be winners and losers, and a public authority must make a defensible decision. Either way, the process fails if it never reaches a conclusion—or if its conclusion becomes disposable as soon as political authority changes hands.
When an Approval Doesn’t Hold
Permitting debates tend to reward what can be counted. An agency can announce that its review was completed in eighteen months instead of thirty; a president can promise a decision in twenty-eight days; a developer can hold up a signed authorization. None of those measures tells us whether the project will be finished or whether the authorization will survive long enough to justify the money and trust invested in it. A permitting system’s ultimate product is not paper approvals. It is decisions that people can rely on.
Consider Mountain Valley Pipeline. It obtained a certificate from FERC, but courts vacated or found defects in several other federal authorizations. That is a reminder that a federal certificate is not a shield against substantive legal requirements, and that litigation can reveal serious agency error. Congress then intervened through Section 324 of the Fiscal Responsibility Act of 2023, ratifying or directing essential authorizations and sharply restricting judicial review of them. The pipeline ultimately achieved greater legal certainty. But it did so through an extraordinary legislative measure that curtailed avenues of legal challenge. Durability obtained by limiting review is not the same as durability earned through a decision that withstands review. Both the original agency failures and the congressional response deserve scrutiny.
Offshore wind illustrates the danger from a different direction. Vineyard Wind 1 and Revolution Wind had secured major federal approvals and undertaken substantial investment when the second Trump administration imposed stop-work or suspension orders on offshore-wind activity. Revolution Wind faced orders in August and December 2025 and obtained preliminary judicial relief in September 2025 and again in January 2026, allowing work to resume while the merits remained in litigation. The developer reported first electricity deliveries in March 2026. Its estimates of millions in daily losses during an earlier halt illustrate the financial exposure, although they are sponsor estimates for this project, not a national cost figure. Those orders were not simply the consequences of a long NEPA review. They interrupted work after the government had already authorized major commitments. Both projects reached full commercial operation in October 2026, yet completion has not settled the matter. That month the Interior Department asked the court to return Revolution Wind’s construction and operations plan approval to the agency for reconsideration, a request still pending.
The administration’s actions have not all pointed in the same direction. The DOI introduced emergency procedures for some geothermal projects and required additional high-level review for wind and solar decisions. EPA approved Texas to administer its own Class VI carbon-storage permitting program. But for the question we’re asking, halting a previously approved project already under construction is more consequential than announcing a faster procedure for a different technology. The former directly tests whether a government’s authorization can support a long-lived investment. Courts granting preliminary injunctions do not necessarily settle the ultimate legality of the suspensions. They do underscore that an agency cannot treat an earlier approval as legally meaningless merely because policy priorities have changed.
Nor is the broader problem exclusive to one party. Administrations of both parties have imposed restrictions on future development they do not favor. But choices about future leasing or permitting and suspensions of already approved construction are not equivalent. Their consequences for investment expectations and reliance differ. The standard should be applied consistently, without matching unrelated actions simply to produce a politically balanced paragraph.
It would be equally wrong to argue that every approval should be irreversible. Agencies need lawful authority to respond to newly discovered hazards and changing conditions; courts must be able to remedy violations; communities must have meaningful opportunities to object. Those safeguards are part of what makes a decision legitimate. The question is whether the grounds for revisiting a decision are specified by law and supported by evidence, rather than invented after the fact to reverse a political predecessor’s priorities. Speed and permanence purchased at the expense of legality can create their own instability. The Senate bill takes up this question directly. Senator Heinrich’s fact sheet says it would bar any administration from blocking permits for a whole class of energy projects without facing legal action and fines. As passed by the Senate on November 19, the bill would bar agencies from revoking or materially altering a permit in effect on or after November 6, 2026, except in listed cases such as a court order, a material violation of the permit or the law, or fraud.
For developers and lenders, uncertainty raises real risks. A delay can extend interest during construction, increase carrying costs, force engineering changes, strand equipment, and postpone revenues. For utilities, some of those costs may eventually be reflected in regulated rates. But we have found no reliable national estimate establishing a specific cost-of-capital premium caused only by permitting delay. The mechanism is credible without attaching a manufactured percentage to it. A plant expected to operate for thirty or forty years will outlast several presidencies. Investors know that; so do communities negotiating jobs, tax revenue, and environmental commitments.
A system unable to say no is not credible. Neither is a system in which a lawful, well-supported yes can be undone for reasons unrelated to the rules under which it was granted. The standard is therefore more demanding than speed: decisions reached competently and fairly, open to appropriate review, with predictable grounds for revision, and substantial enough to bear the weight of the investments and public expectations placed upon them.
The America We Could Build
The diagnosis has four parts. First, projects must navigate a chain of federal, state, local, and private decisions that no single institution reliably coordinates. Second, agencies and affected communities sometimes lack the people, institutional knowledge, and information needed to do their jobs. Third, permitting must settle genuine conflicts over land, water, environmental protection, property, costs, and political authority. Fourth, even a project that completes the process may discover that its approvals are more vulnerable than the law and its investment plans led it to expect. A narrower NEPA review may help at one point in that chain. It cannot substitute for making the chain work.
What would improvement look like? A geothermal office would know where its applications stand and have experienced people able to evaluate them. A carbon-storage permitting program would have technical staffing commensurate with its workload. A long-distance transmission project would have an intelligible critical path and institutions accountable for the decisions they actually control. When one agency held up a decision that others had finished, someone would have the authority to resolve it. A tribal government would have the resources to exercise its legal rights meaningfully, rather than being told it had been consulted after the practical choices were made. Nearby communities would hear about a project before its sites were chosen and its land secured, not after. And a developer that had received a lawful approval—whether for a pipeline or an offshore wind farm—would know the conditions under which that approval might subsequently be challenged or changed. None of this promises a yes. It promises a decision worthy of being made.
That prospect matters for electricity bills, reliability, AI, manufacturing, and the work of reducing and adapting to climate change. The infrastructure we need will not all be popular, and some proposals should fail. An effective democracy must be able to say no when the law and evidence warrant it, and to make that refusal meaningful. It must also be able to say yes after a fair process and not force everyone to start over whenever political power changes hands. Participation cannot be theater. Nor can every unresolved disagreement become an indefinite veto.
China can often move industrial decisions through centralized authority faster than the United States can move them through its divided institutions. That speed can conceal costly mistakes and deny communities meaningful recourse; centralized power is no guarantee of sound or lasting decisions. Our ambition should not be to copy finality imposed from above. It should be to achieve reliability through legitimacy: decisions that hold because competent institutions reached them lawfully, gave affected people a fair hearing, and retained only the grounds for reconsideration the law actually permits.
The test of American permitting is not how quickly a government can say yes. It is whether its answers—yes or no—are worth relying on. A democracy that could meet that test would have something more valuable than a faster stamp: the institutional confidence to build responsibly, and to finish what it has legitimately decided to build. Our forthcoming second paper tests the Senate bill and other pending proposals against these four causes and sets out what reform would need to contain to meet that test.
Appendix A — Six Case Families, Different Mechanisms
Selected illustrations, not a statistical sample. Dates and legal postures are based principally on Sections 8.1–8.6 and the source notes of Doyle and Eccles, The Cost of Delay, supplemented where indicated by 2026 developments. This is the evidentiary companion to the cases distributed across Sections III, V, VI, and VII, not additional main-text narrative. EIS means environmental impact statement; EA means environmental assessment; NEPA means the National Environmental Policy Act; NGO means nongovernmental organization; BLM means Bureau of Land Management; EPA means Environmental Protection Agency; FERC means Federal Energy Regulatory Commission.

Gemini Solar: a process that reached a conclusion
Gemini Solar is a utility-scale solar project on federal land northeast of Las Vegas. The Bureau of Land Management’s environmental impact statement addressed effects on desert tortoise habitat, migratory birds, and resources important to tribal communities. BLM selected a hybrid design, modifying the project’s footprint rather than treating review as a formality. The draft EIS appeared in June 2019 and the record of decision in May 2020; that eleven-month interval measures draft EIS to decision, not the full environmental-review period. The larger point is that substantial review and eventual construction were compatible. This is the positive counterexample, not a universally replicable schedule. Phase I §8.5; EIA, Today in Energy, Aug. 7, 2026.
SunZia: agency conflict is not the same as a single long review
SunZia’s right-of-way history began in 2008. The BLM process analyzed a large transmission route across the Southwest; a late conflict with the Department of Defense over activities at White Sands Missile Range required further examination and accommodation, including additional environmental assessment and a finding of no new significant impact. This was not outside the NEPA process: interagency conflict generated more NEPA-related work. At other points, sponsor decisions, a change of owner, technological redesign, and further approvals influenced the project. Subsequent litigation over historic-preservation duties presents still another legal issue. The phrase “an eighteen-year NEPA review” collapses these different periods into a misleading whole. Phase I §8.1.
Class VI: an agency needs the ability to do the work
Class VI permits under the Safe Drinking Water Act regulate injection wells used for permanent geologic storage of carbon dioxide. Applications increased sharply following the expansion of carbon-storage projects and financial incentives. EPA’s inspector general found that complex technical questions, incomplete applications, applicant response times, staffing, and modeling capacity affected the agency’s ability to meet its approximately 24-month administrative review goal for some applications. The goal is not a universal statutory deadline. This case illustrates a problem of technical capability rather than a story principally about lawsuits. It also helps explain why an agency can respond to an increased workload more effectively through competent administration than through a decree to review more rapidly. EPA Office of Inspector General, 2025; Phase I §8.2.
Thacker Pass: federal success, state-law constraints, disputed legitimacy
BLM approved the lithium project in January 2021. Environmental, ranching, and tribal challenges raised different questions of groundwater, wildlife, land authority, and consultation. Federal courts largely sustained the agency’s approval, with a narrower remand concerning rights to use certain land and no general halt to construction. In separate Nevada proceedings, a rancher’s water-rights challenge prompted restrictions and a cease-and-desist order on pumping, followed by subsequent resolution; construction continued. Tribal disagreements persisted despite federal litigation outcomes, including objections concerning a site that tribal nations associate with an 1865 massacre at Peehee Mu’huh. The state-law order was consequential, but it must not be transformed into an invented complete work stoppage. More fundamentally, a court’s determination of legal sufficiency is not the same as public acceptance. Phase I §8.3.
Mountain Valley Pipeline: legally defective approvals and extraordinary finality
FERC issued the interstate natural-gas certificate in October 2017. Several companion federal authorizations were subsequently vacated by the Fourth Circuit after the court found defects in agency analysis, including decisions involving national forest crossings, water-related authority, and endangered-species review. In 2023 Congress ratified remaining federal authorizations in the Fiscal Responsibility Act and restricted judicial review in an unusually project-specific intervention. The pipeline entered service in June 2024. It is an example of how a centralized federal certificate can coexist with vulnerability in the authorizations a project still needs. It is also a warning against treating judicial correction of real legal errors as inherently illegitimate. Phase I §8.4.
Offshore wind: subsequent executive decisions and the limits of finality
Vineyard Wind 1 received its principal federal decision in May 2021 and successfully defended that original approval through litigation, including a Supreme Court denial of review in January 2025. Its development history was not free of private choices: in late 2020 the sponsor paused part of the federal process while considering larger turbines. A separate blade failure in 2024 was an operational event. Following a December 2025 offshore-wind suspension order, Vineyard Wind obtained judicial relief in January 2026; construction of the turbines was completed by May 2026. The project reached commercial operation at partial capacity in April 2026 and full commercial operation on October 29, 2026. A separate contract dispute with its turbine supplier, GE Vernova, was settled in September 2026.
Revolution Wind was far advanced when it received a federal stop-work order in August 2025 and was suspended again in December. The courts granted preliminary relief allowing construction to resume. The developer’s sworn estimates of losses and costs reflect its claims in those proceedings, not adjudicated national costs. The company reported first delivery of electricity in March 2026 and full commercial operation in October 2026. That same month, the Interior Department asked the federal court to return the project’s construction and operations plan approval to the agency for reconsideration, citing the Outer Continental Shelf Lands Act rather than the national-security grounds of the earlier orders; the request remains pending. These cases involve subsequent executive authority and judicial remedies, not simply the length of an original environmental review. Phase I §8.6; Revolution Wind injunction announcement; Revolution Wind first power; Vineyard Wind court docket; Vineyard Wind full commercial operation; Interior remand request; Revolution Wind full commercial operation.
Appendix B — Capacity, Investment, and Measurement Notes
The flagship table in the essay is intentionally not a consolidated forecast of “what must be built by 2035.” That would require a harmonized portfolio of demand, reliability, emissions, retirement, and cost assumptions that the underlying sources do not provide. The figures below establish scale while recording the different measurements.

Key definitions. A gigawatt (GW) measures capacity or power, while a terawatt-hour (TWh) measures energy consumed or generated over time. A battery’s GW rating does not tell us how many hours it can discharge. Net summer capacity, nameplate power, and time-adjusted annual capacity are distinct EIA measures. Transmission line miles are a physical construction measure; TW-miles account for power-transfer capability over distance. Gross new capacity additions are not net growth because plants also retire. Neither a model’s projected output nor an active interconnection request is proof of a physical requirement.
Investment boundaries. EIA’s 2024 technology-specific installed-construction costs are historical averages, not future all-in project prices. Actual costs depend on technology and configuration, financing, land, battery duration, interconnection, labor, and price changes. The earlier HIT workbook used the 2026 construction plan as a hypothetical ten-year run rate, producing numerical cost sensitivities. Gemini correctly identified why those extrapolations could be mistaken for genuine forecasts. They have been retired from the public argument, not converted into national “needs.” Likewise, the utility-capital-expenditure outlook overlaps generating-facility spending and must not be added to it. Perplexity caught and we corrected an earlier error about EEI’s historical “gas-related” functional category: it includes gas delivery and pipeline infrastructure but excludes natural-gas-fired electricity generation in the cited vintage.
Appendix C — Institutions, Politics, and Evidence Boundaries

Selected actions under the second Trump administration, stated without an evaluation of overall merit: The Interior Department announced accelerated procedures for some geothermal projects in May 2025; issued a July 2025 memorandum requiring higher-level review of wind and solar decisions; and subsequently suspended offshore wind activities that were challenged in court. DOE shifted National Environmental Policy Act implementation procedures in 2025 and updated them in July 2026. EPA issued specific Texas Class VI permits, then approved Texas to administer the Class VI program in a final rule signed November 7, 2025. The effects of these actions are not captured by one measure: announced acceleration, enacted rule, transferred jurisdiction, project approval, and suspended construction have different meanings. See the agency source links embedded in the main essay.
The personnel and institutional-capacity evidence
GAO’s October 2026 geothermal review, together with its public explanatory note, documents permitting inconsistencies, staff constraints in particular field offices, and the absence of a unified tracking system. The EPA inspector general’s Class VI review documents the disparity between growth in specialist positions and growth in pending applications. A BLM workforce-planning review provides historical evidence about headquarters vacancies and guidance delays; those historic vacancy figures must not be misrepresented as a current nationwide shortage. GAO’s 2026 geothermal review adds that BLM had paused its strategic workforce plan as of May 2026. GAO’s offshore-wind report documents both agency engagement problems and the inadequate resources reported by nearly all the tribal representatives it interviewed. None of these studies supplies an all-sector national shortage estimate or a quantified rate of staff departures to industry. The personnel section in the main essay deliberately distinguishes localized evidence from national inference.
State politics and the distribution of costs. The EIA’s planned 2026 solar and battery geographic distributions provide counterexamples to any simplistic equation of conservative states with hostility to all clean-energy deployment. They do not establish which state’s permitting system is faster. Interconnection queues also reflect technology, resource quality, utility geography, commercial interest, and speculative applications. No harmonized national causal estimate was located that assigns energy affordability losses from permitting delays by household income, red/blue affiliation, or rural/urban location. Readers should be told what remains unknown rather than given false precision.
Environmental lawsuits. Rea, Merten, and Rife (2024) count 25,775 federal environmental civil suits from 1988 to 2022 and report approximately 26.2% with environmental NGO plaintiffs, across many statutes. The Breakthrough Institute’s NEPA case analysis examines a selected narrower litigation dataset and reports NGO involvement in roughly three-quarters of its judgments. Those samples cannot be substituted for each other. Litigation frequency does not measure attributable construction delay; judgments for agency error can protect valuable legal rights. The correct questions are which challenged projects, what courts found, and what consequences followed.
Legal scope. The Major Questions Doctrine limits certain consequential assertions of authority absent sufficiently clear congressional authorization. Its relevance to air-pollution permitting and major regulatory actions does not make it the general standard for suspending an individual existing permit. The immediate legal questions are ordinarily the relevant statute, applicable approval or lease terms, the Administrative Procedure Act, and specific judicial remedies. The main essay deliberately leaves this distinction at the level of ordinary language; additional doctrine belongs in Tim’s legal review and future research, not a standalone section.
Appendix D — Who Wrote This Essay?
There is a straightforward institutional answer. Timothy M. Doyle and Robert G. Eccles wrote and are responsible for the essay that bears their names. They decide what they are prepared to say publicly, whether the evidence supports it, and what changes to make before publication. But that conventional answer leaves out how the argument and the writing developed. It is also why the familiar question—Was this written by a human or by AI?—doesn’t tell us much about this kind of work.
We organized the project as a Hybrid Intelligent Team (HIT): two human coauthors and several AI agents with differentiated but adjustable responsibilities. Dorothy (ChatGPT) served as Principal Collaborating Agent, coordinating research, drafting, checking and integrating the work. Claude provided structural criticism and a substantial editorial revision; Gemini independently attacked factual claims and then challenged the capacity-and-cost model; Perplexity checked primary sources and extracted government spreadsheets. The agents were not simply copy editors. At times they identified an argument we had not sufficiently recognized or a flaw in our quantitative presentation. At other times they were wrong, incomplete, overly cautious, or too ready to optimize the wrong thing.
One incident captures the process better than a disclosure saying “AI was used.” Our original essay included approximately 1,400 words on six case-study families. The machines debated their order, refined the transitions, added missing evidence, and improved the section by conventional editorial criteria. Then Eccles read the full essay as a reader, not as a permitting specialist, and identified the larger failure: the piece was careful and accurate but too tedious to engage a general audience, and the case-study section stopped its momentum. Reordering six detailed studies was no answer when what the essay needed was to move the evidence into an appendix and give readers a much stronger reason to care about permitting in the first place.
That was not a request to make a few sentences more lively. It changed the intellectual assignment. Eccles redirected the narrative toward electricity affordability and reliability, climate mitigation and adaptation, AI infrastructure, and competition with China. Dorothy was then tasked with constructing a new research program and architecture, rather than cosmetically polishing the previous version. Gemini and Perplexity were assigned different reviews; their findings altered both what the essay said and what it declined to claim. Whether any iteration succeeds as writing is something the human authors and readers still must judge. It cannot be inferred from the sophistication of its production process.
A later revision also revealed a second-order capacity constraint: experienced officials and communities need the resources to administer and participate in permitting. Eccles raised the omitted dimension; Dorothy researched federal oversight findings and integrated a new section. Another observation concerns layered HITs: some sources we draw upon—including earlier essays and the Phase I report—were themselves products of previous human–AI teams. A present-day word-by-word disclosure cannot exhaust that history of intellectual influence.
The team also changed as it worked. After the case-study episode, Claude’s future editorial assignment was revised: challenge the purpose and structure of the whole essay before improving local sections. In a new conversation, with only the main manuscript and a deliberately independent editorial brief, Claude made a pointed criticism of Draft 2.1: it had become a document written to survive its reviewers rather than persuade readers. He recommended dissolving the remaining six-case section, moving NEPA earlier, defining the diagnosis explicitly, and removing the many qualifications that had accumulated from earlier adversarial checks. The irony was useful: Claude had earlier helped refine the structure he now argued should be eliminated. The revision to Draft 2.2 adopted much of his structural diagnosis but retained the broader four-part account of permitting failures rather than making durability the sole explanation.
The episode also exposed a limitation in Dorothy’s role as Principal Collaborating Agent. The PCA had integrated successive rounds of technically sound criticism without detecting that the combined effect was weakening the argument’s rhetorical force. Asking a collaborator deeply involved in production to ‘remember to check the forest’ might help, but it does not recreate the independence of a fresh critic instructed to question the entire manuscript. That is a workflow issue, not proof of an inherent inability of any model to assess its own work. Perplexity was tested in a limited source-verification role rather than assumed reliable or unreliable based on earlier experiences. Dorothy began maintaining a running Decision and Contribution Log, including mistakes and rejected proposals as well as accepted changes. The Human Coherence Anchor and Principal Collaborating Agent were not merely managing a fixed division of labor; they were examining whether the team’s organization itself was helping or hindering the work.
This is a small instance of what might be called reflexive HIT governance. It is a working observation, not a demonstrated general theory. We cannot neatly separate improvements in model capability from better instructions, better tools, accumulated context, or the human’s growing experience. Nor does an agent’s contribution to an idea give it professional or legal responsibility for the result. Intellectual contribution and accountability remain different questions.
In The Artisanal Paper Is Dead, Eccles and Shivaram Rajgopal argue that conventional rules requiring an exhaustive accounting of how AI was used are increasingly unsuited to knowledge produced through extended human–machine interaction. An honest history of this modest Substack essay could itself be longer than the essay. This appendix does not pretend to be that history. It records a few decisions that materially changed the finished work and offers readers a more informative question than who typed which sentence: What did each participant contribute, what was tested, and who stands behind the result?
About Tim Doyle
Timothy M. Doyle is a Co-Founder of the Responsible Business Initiative (RBI) and the Founder and Principal of Doyle Strategies, a governance and public policy advisory firm. A lawyer and public policy expert, he has more than 20 years of experience advising Fortune 500 companies and other stakeholders on corporate governance, securities law, and financial regulation. He previously served as Staff Director and Senior Counsel on two U.S. House of Representatives committees, has testified before Congress, and writes frequently on securities and financial regulation.
This is the public content supplied by Substack. Any subscriber-only content remains on Substack.











































































































































































